IN THE PUNJAB AND HARYANA HIGH COURT AT

CHANDIGARH CWP-4384-2023 Date of Decision: 08.01.2024  ... Petitioner

VERSUS

       ... Respondents CORAM: HON'BLE MR. JUSTICE VINOD S. BHARDWAJ. ****     

                    

       

 !

"#     

$ %      &  '(     )*     

+    

  

,  ---- VINOD S. BHARDWAJ, J. (ORAL) Prayer made in the present petition is for directing the respondents to take immediate action in furtherance of the complaints dated 09.02.2023 and 10.02.2023 and the letter dated 11.02.2023 in order to ensure that proper and adequate safety measures are installed at the construction/excavation site for the Dadri-Rewari Phase-2 project near village Sehsaula and Dhulawat, District Nuh.

Learned counsel appearing on behalf of respondent No.6 contends that the proper measures are being undertaken to install the safety measures and that the said work is being expedited. He further assures that the said work shall be completed within a period of two months. RAJENDER KUMAR 2024.01.10 12:05 I attest to the accuracy and authenticity of this document

    



  In view of the aforesaid statement made by learned counsel for respondent No.6, the counsel for the petitioner contends that his grievance has been redressed and as such, the present petition has become infructuous. Disposed of as having been rendered infructuous.             

   