2023:PHHC:152991 In the High Court of Punjab and Haryana, at Chandigarh Civil Revision No. 1116 of 2021 (O&M) Date of Decision: 01.12.2023 Sandeep ... Petitioner(s)

Versus

Dakshin Haryana Bijli Vitran Nigam Limited ... Respondent(s) CORAM: Hon'ble Mr. Justice Anil Kshetarpal.

Present:

Mr. Ramesh Hooda, Advocate for the petitioner(s).

Mr. R.D.Bawa and Mr. Randhir Bawa, Advocates for the respondent.

Anil Kshetarpal, J.

1.

The learned counsel representing the respondent has informed the Court that the electric poles have been installed and laying of the overhead power lines to carry 33kv electric current has been completed, therefore, the present revision petition is rendered infructuous. 2.

The learned counsel representing the petitioner does not dispute the aforesaid factual position. However, he submits that the Court should issue a direction to change the alignment of the power lines, if possible. 3.

This Court has considered the submissions of the learned counsel representing the parties. At this stage, only an application for the grant of temporary injunction has been dismissed. The petitioner, if so advised, may make a request to the trial Court while finally deciding the case.

DEEPAK KUMAR BHARDWAJ 2023.12.04 11:05 I attest to the accuracy and integrity of this document

2023:PHHC:152991 Civil Revision No. 1116 of 2021 (O&M) 4.

With the observations made above, the present revision petition is disposed of.

5.

The miscellaneous application(s) pending, if any, shall also stand disposed of.

(Anil Kshetarpal) Judge December 01, 2023 "DK"

Whether speaking/reasoned :Yes/No Whether reportable : Yes/No DEEPAK KUMAR BHARDWAJ 2023.12.04 11:05 I attest to the accuracy and integrity of this document