High Court of Punjab and HaryanaCWP/10730/2022disposed of

The Shahabpur Cooperative Labour And Construction Society Limited v. Municipal Corporation,Amritsar Through Its Commissioner And Another

2022-05-19Mr. Justice Raj Mohan Singh2 pages

CWP No. 10730 of 2022 -1IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH CWP No. 10730 of 2022 Date of Decision: 19.05.2022 The Shahabpur Cooperative Labour and Construction Society Limited -Petitioner

Versus

Municipal Corporation, Amritsar and another -Respondents CORAM: HON'BLE MR. JUSTICE RAJ MOHAN SINGH

Present:

Mr. Dheeraj Mahajan, Advocate, for the petitioner.

Mr. Sanjeev Soni, Advocate, for respondents No.1 and 2.

**** RAJ MOHAN SINGH, J. (Oral) Grievance of the petitioner is that despite preparation of final bill, the same has not been released to the petitioner. Learned counsel for the petitioner submits that the legal notice got issued by the petitioner is still pending before respondent No.2 and at this stage, the petitioner would be satisfied in case its legal notice is ordered to be decided by respondent No.2 in accordance with law.

Learned counsel for respondents No.1 and 2 submits that the legal notice got issued by the petitioner shall be decided within four weeks in accordance with law.

JYOTI SHARMA 2022.05.20 17:41 I attest to the accuracy and integrity of this document

CWP No. 10730 of 2022 -2With this observation, this writ petition is disposed of. If the payment is ultimately found to be delayed payment and delay is attributable to the respondents, then the petitioner shall be paid interest @ 6% per annum for the delayed payment from the date of accrual till final realization of the amount.

19.05.2022 (RAJ MOHAN SINGH) Jyoti Sharma JUDGE Whether speaking/reasoned :

Yes/No Whether reportable :

Yes/No JYOTI SHARMA 2022.05.20 17:41 I attest to the accuracy and integrity of this document