Baljinder Singh And Others v. Union Of India And Others
-1CWP-11887 of 2020
IN THE HIGH COURT OF PUNJAB AND HARYANA
AT CHANDIGARH CWP-11887 of 2020 Date of Decision: 03.08.2022 Baljinder Singh and others
...Petitioners
Versus
Union of India and others ....Respondents CORAM: HON'BLE MS. JUSTICE RITU BAHRI HON'BLE MR. JUSTICE ASHOK KUMAR VERMA Present:- Mr. Arun Kumar Vasudeva, Advocate, for the petitioners.
Mr. Arvind Seth, Advocate, for respondent No.1.
Mr. B.S. Jolly, Advocate, for respondents No.2 and 3.
RITU BAHRI, J. (ORAL) Learned counsel for respondents No.2 and 3 states that vide letter dated 21.04.2022 Controller of Explosives has informed that installation/laying of the pipeline has been completed and the report of hydro tests conducted of the said pipelines has been confirmed as being satisfactory. A copy of the letter is taken on record as Annexure R-1 and a copy of the same has also been supplied to learned counsel for the petitioners.
In view of the above, no further directions are required to be RAVINDER SINGH 2022.08.08 10:20 I attest to the accuracy and authenticity of this order/judgment
-2CWP-11887 of 2020 given in this writ petition.
Disposed of.
(Ritu Bahri) Judge (Ashok Kumar Verma) August 03, 2022 Judge R.S.
Whether speaking/reasoned Yes/No Whether Reportable Yes/No RAVINDER SINGH 2022.08.08 10:20 I attest to the accuracy and authenticity of this order/judgment