M/S Seema Engineering Works v. State Of Haryana & ORS.
IN THE HIGH COURT OF PUNJAB & HARYANA AT CHANDIGARH
Civil Writ Petition No.6530 of 2006 (O&M).
Date of Decision: November 30, 2016 M/s Seema Engineering Works and others ......Petitioners versus The State of Haryana and others .....Respondents CORAM: HON'BLE MR.JUSTICE SURYA KANT.
HON'BLE MR.JUSTICE SUDIP AHLUWALIA.
*** Present: Mr.Aashish Chopra, Advocate, for the petitioners. Ms.Palika Monga, DAG, Haryana.
-.-
1. Whether Reporters of Local papers may be allowed to see the judgment?
2. To be referred to the Reporters or not?
3. Whether the judgment should be reported in the Digest? --- Surya Kant, J . (Oral) The petitioners have laid challenge to the acquisition of their land fully described in para No.2 of the writ petition and situated within the revenue estate of village Khandsa, Tehsil and District Gurgaon. The said acquisition was made vide Award dated 27.01.2006. The record reveals that the writ petition was taken up alongwith CWP No.18061 of 2006 and interim order was directed to continue till the next date of hearing.
In the light of the later development, namely, the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (for short, 'the 2013 Act') having come into force w.e.f. 01.01.2014, the additional question which arises for consideration is whether the impugned acquisition shall be deemed to have lapsed under Section 24(2) of the 2013 Act?
CWP No.6530 of 2006 (O&M) [2] Though the compensation amount was duly deposited with the Reference Court on 07.04.2008 but it is the conceded position that the petitioners have a workshop set up on the acquired land and their dispossession was stayed by this Court. Resultantly, the petitioners are still in possession which is continuous and more than five years from the date of passing the Award and before the new Act (2013 Act) came into force w.e.f. 01.01.2014. There can thus be no escape but to hold that the impugned acquisition has lapsed under Section 24(2) of the 2013 Act. For the detailed reasons assigned in the order dated 27.10.2016 passed in CWP No.17464 of 2007 (Satnam Singh and another versus The State of Haryana and others) and connected matters, the instant writ petition is allowed and it is declared that acquisition of the petitioners' land vide Award dated 27.01.2006 is deemed to have lapsed. Having held so, we are surely of the view that since Section 24
(2) of 2013 Act itself, in so many words, contemplates the possibility of reacquisition of the land/property in respect whereof the previous acquisition has lapsed, it is necessary to direct the petitioners to maintain status quo re: creation of third party rights; to keep the land/property free from all types of incumbrances and not to change the nature of land/property for a period of one year so that meanwhile the respondent-State may, if such property is needed for a "public purpose", again acquire it. Such a direction is necessitated also for the reason that in numerous cases State or its agencies have taken possession in part and development works have been executed except over that land/property in litigation. Those development works ought to be completed in public interest and the only consequence of lapsing of previous acquisition, mostly due to fault of the Government Officers/
CWP No.6530 of 2006 (O&M) [3] Officials, would be that the owners of such land/property will be entitled to compensation and other benefits admissible under the 2013 Act. [SURYA KANT] JUDGE November 30, 2016 [SUDIP AHLUWALIA] mohinder JUDGE Whether speaking/reasoned :