← Library
High Court of Punjab and HaryanaARB/207/2019disposed of

M/S Bhullar Constructions v. Executive Engineer Provisional Division Pwd B And R Amritsar And ANR

2022-11-18The Chief Justice1 pages

IN THE HIGH COURT OF PUNJAB & HARYANA AT CHANDIGARH

Arbitration Case No. 207 of 2019 (O&M) Date of Decision: 18.11.2022 M/s Bhullar Constructions, Engineer and Contractors .....Petitioner versus Executive Engineer, Provisional Division, PWD (B&R), Amritsar and another .....Respondents

CORAM:

HON'BLE MR.JUSTICE RAVI SHANKER JHA, CHIEF JUSTICE Present :

Mr. J.S.Rana, Advocate, for the petitioner.

Mr. Avinit Avasthi, Assistant Advocate General, Punjab. ****         This petition has been filed by the petitioner under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of sole arbitrator for adjudication of the dispute that has arisen between the parties from the agreement entered into between them on 02.07.2014. In view of the previous order dated 14.10.2022 passed by this Court, necessary declaration as required under Section 12 of the Act was called from Justice Ajay Kumar Mittal, former Chief Justice of Madhya Pradesh High Court, and the same has been received and placed before this Court.

In these circumstances, Justice Ajay Kumar Mittal, former Chief Justice of Madhya Pradesh High Court, is appointed as Arbitrator to adjudicate upon the disputes between the parties.

Application stands disposed of.

(RAVI SHANKER JHA) CHIEF JUSTICE 18.11.2022 ravinder Whether speaking/reasoned √Yes/No Whether reportable Yes/No√ RAVINDER KUMAR 2022.11.21 15:59 I attest to the accuracy and integrity of this document