← Library
High Court of Punjab and HaryanaCWP/17878/2018dismissed

Anju Gupta v. M/S The New Engineering Works And ORS

2018-09-27Mr. Justice Karamjit Singh1 pages

In the High Court of Punjab and Haryana, at Chandigarh Civil Writ Petition No. 17878 of 2018 Date of Decision: 27.09.2018 Anju Gupta ... Petitioner(s)

Versus

M/s The New Engineering Works and Others ... Respondent(s) CORAM: Hon'ble Mr. Justice Shekher Dhawan.

Present:

Mr. Yashveer Kharb, Advocate for the petitioner(s).

Shekher Dhawan, J.

Present writ petition is to challenge the impugned award dated 21.07.2008 (Annexure P5) and order dated 23.07.2012 (Annexure P10). Learned counsel for the petitioner, while arguing on the point of delay of ten years, contended that different applications were filed for recalling of the aforesaid orders and the same were dismissed for want of prosecution on the part of petitioner himself. As such, there is no justified ground for condonation of delay on this ground. The petitioner has failed to give any valid explanation for such a long delay. In view of the law laid down by Hon'ble the Apex Court on the point of delay and latches, in Nedungadi Bank Ltd. Vs. K.P. Madhavankutty and Others AIR 2000 SC 839, present petition stands dismissed.

(Shekher Dhawan) Judge September 27, 2018 "DK"

Whether speaking/reasoned :Yes/No Whether reportable : Yes/No DEEPAK KUMAR BHARDWAJ 2018.09.27 16:35 I attest to the accuracy and integrity of this document