-1IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH CWP No. 629 of 2017 (O&M) Date of decision : 27.11.2017 Randhir Singh .. Petitioner versus State of Haryana and others .. Respondents Coram:

Hon'ble Mr. Justice Rajesh Bindal Hon'ble Mr. Justice Gurvinder Singh Gill

Present:

Mr. Sandeep Panwar, Advocate, for the petitioners. Mr. Ankur Mittal, Additional Advocate General, Haryana with Mr. Shivendra Swaroop, Asstt. Advocate General, Haryana and Mr. Manoj Dhankhar, Assistant Advocate General, Haryana. Rajesh Bindal, J.

The petitioner has filed the present petition claiming that in view of the provisions of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (for short, 'the 2013 Act'), the acquisition has lapsed, as the petitioner has neither been paid compensation for the acquired land nor possession thereof has been taken from him. Notifications under Sections 4 and 6 of the Land Acquisition Act, 1894 (for short, 'the 1894 Act') were issued on 9.8.2002 and 8.8.2003, respectively. Award was announced by the Land Acquisition Collector (for short, 'the Collector') on 5.8.2005. Learned counsel for the petitioner submitted that neither compensation for the acquired land has been paid to the petitioner nor

-2possession thereof has been taken from him. It was submitted that the petitioner had purchased a plot measuring 9 marlas and constructed a pucca house over the plot in question much before the acquisition. The petitioner is still in physical possession of the plot.

Learned counsel for the State did not dispute the fact that the compensation for the acquired land has not been paid to the petitioner. It was not disputed that construction was existing on the plot in question prior to issuance of notification under Section 4 of the 1894 Act. He further did not dispute the fact that the petitioner is still in physical possession of the plot.

Heard learned counsel for the parties and perused the paper book.

Section 24(2) of the 2013 Act provides that acquisition of land would lapse in cases where award had been announced by the Collector five years prior to the enactment of the 2013 Act i.e. 1.1.2014, in case either the compensation for the acquired land has not been paid or the possession thereof has not been taken.

In the case in hand, it is admitted position on record that compensation for the acquired land has not been paid to the petitioner. As regards possession of the land is concerned, it is not in dispute that the petitioner is in possession of the land prior to issuance of notification under Section 4 of the 1894 Act as construction had been raised thereon. For the reasons mentioned above, in our opinion, ingredients as contained in Section 24(2) of the 2013 Act having been complied with, the

-3acquisition of land in question has lapsed. The writ petition is allowed.

(Rajesh Bindal) Judge (Gurvinder Singh Gill) Judge 27.11.2017 sharmila Whether speaking/reasoned :

Yes/No Whether reportable :

Yes/No