Pankaj Arora Builders And Govt v. State Of Punjab And ORS.
IN THE HIGH COURT OF PUNJAB AND HARYANA AT
CHANDIGARH CWP-5015-2018 (O&M) Date of decision:- 01.03.2018 Er. Pankaj Arora Builders and Govt. Contractor
...Petitioner
Versus
State of Punjab and others
...Respondents
CORAM: HON'BLE MR. JUSTICE S.J. VAZIFDAR, CHIEF JUSTICE HON'BLE MR. JUSTICE AVNEESH JHINGAN Present:- Mr. P.S. Rana, Advocate, for the petitioner.
* * * * S.J. VAZIFDAR, C.J. (ORAL) The petitioner has challenged the respondents' decision to abandon the tender process to invite fresh bids. The petitioner also seeks an order directing the respondents to award the contract in its favour.
2.
The respondents by an office order directed the cancellation of the tender process on the ground that the Executive Engineer had committed serious violations in respect of the tender process. It was also decided to invite the fresh bids. 3.
A bidder is not entitled as a matter of right to be awarded a contract merely because his bid is the lowest. Admittedly, a contract was not entered into between the parties. 4.
The petitioner is not prejudiced in any manner for it can participate in the fresh tender process.
5.
The petition is accordingly dismissed.
(S.J. VAZIFDAR) CHIEF JUSTICE (AVNEESH JHINGAN) JUDGE 01.03.2018 Amodh Whether speaking/reasoned Yes/No Whether reportable Yes/No Amodh Sharma 2018.03.01 17:02 I attest to the accuracy and integrity of this document Chandigarh