The H.P Cooperative Labour And Construction Society Ltd. v. Jaspreet Kaur Talwar And ORS
IN THE HIGH COURT OF PUNJAB AND HARYANA AT
CHANDIGARH COCP-2885-2020 Date of Decision: 23.02.2021 The H P Cooperative Labour and Constrction Society Ltd. ......Petitioner
Versus
Jaspreet Kaur Talwar and others .....Respondents CORAM: HON'BLE MR. JUSTICE HARINDER SINGH SIDHU
Present:
Mr. Chirag Girdhar, Advocate for the petitioner.
Ms. Deepali Puri, Addl. A. G., Punjab.
HARINDER SINGH SIDHU, J The petitioner had filed a writ petition bearing CWP-13492 of 2020 seeking a writ of Mandamus directing the respondents to release the due payment of the petitioner as mentioned in the head note of the petition, which was disposed of by this Court on 09.09.2020 with a direction to the respondents to examine the claim of the petitioner as detailed in the legal notice and take a decision thereon.
A reply on behalf of the respondent- State of Punjab has been filed in which it has been stated that a speaking order in respect of the claim of the petitioner has been passed on 18.12.2020. The amount due to the petitioner has been calculated at Rs. 58,80,000/-. Out of the said amount, a sum of Rs. 30,00,000/- was released to the petitioner whereas remaining amount of Rs. 20,80,000/- has been sent to the Treasury also for making payment to the petitioner.
In view thereof, present petition is disposed of as having become infructuous.
Needless to say, it would be open to the petitioner to avail of any appropriate remedy, in accordance with law, if still aggrieved. February 23, 2021 (Harinder Singh Sidhu) manoj Judge Whether speaking/reasoned: Yes/No Whether Reportable: Yes/No MANOJ KUMAR 2021.02.24 09:38 I attest to the accuracy and integrity of this document