Sk Alomgir v. State Of West Bengal And ORS.
Sl. No.114 08.01.2025 Suman Ct. 15 WPA 516 of 2025 Sk. Alomgir Vs.
The State of West Bengal and Ors.
Mr. P. Biswas Mr. Syed Murshid Alam Mr. Nobiul Islam Mr. Subrata Ghosh Ms. Amrita Sen ..for the petitioner Mr. Sudipta Panda Mr. P.K. Tripathi .for the State The petitioner challenges an order dated January 2, 2025, issued by the Maheshtala Municipality. The petitioner contends that although they have completed the demolition of the unauthorized construction, the Municipality has issued another order on January 2, 2025, directing further demolition of the same construction. A cursory review of the notice dated January 2, 2025, clearly indicates that the petitioner has not yet completed the demolition work.
Consequently, the petitioner has been directed to complete the demolition by January 10, 2025. The Municipality has further stated that if the demolition is not completed by the petitioner by that date, it will
commence the demolition of the illegal structure on January 16, 2025, and continue until the work is fully executed.
The petitioner has not contested the original demolition order, dated November 19, 2024. As a result, the original demolition order must be implemented. In light of the foregoing, no interference is warranted.
Accordingly, WPA 516 of 2025 is dismissed.
Urgent photostat certified copy of this order, if applied for, be supplied to the learned advocates for the parties on usual undertakings.
(Kausik Chanda, J.)