Calcutta High CourtWPA/1766/2021disposed

Mihir Ranjan Bala v. State Of West Bengal And ORS.

2021-02-26Hon'Ble Justice Amrita Sinha3 pages

26.02.2021.

d.p.

W.P.A 1766 of 2021 (Via Video Conference) Mihir Ranjan Bala -versus The State of West Bengal & Ors.

Mr. Md. Sarwar Jahan, ...For the Petitioner.

Mr. Ziaul Islam, Mr. A.H. Molla.

...For the State.

Mr. Monoj Kr. Roy.

...For the Respondent Nos. 10 and 11.

Affidavit-of-service filed in Court today is taken on record.

The petitioner alleges illegal and unauthorized construction being carried on in L.R. Plot No. 511, J.L. No. 42, Mouza-Bora within Ichapur II Gram Panchayat under Gaighata Block, North 24-Parganas.

The petitioner complains that the objection raised against such illegal construction has not been considered by the respondent authorities till date. The learned advocate appearing for the private respondents however denies the allegation of illegal construction.

As it appears that the representation of the petitioner objecting to the illegal and unauthorized construction is pending consideration at the end of the

respondent authorities, no useful purpose will be served by keeping the writ petition pending.

The writ petition is accordingly disposed of by directing the respondent no.8 to consider and dispose of the representation made by the petitioner, strictly in accordance with law, after giving an opportunity of hearing to all the necessary parties, including the petitioner, within a period of twelve weeks from the date of communication of a copy of this order. The said respondent shall pass a reasoned order and communicate the same to all the necessary parties, including the petitioner, immediately thereafter. In the event the aforesaid respondent is of the considered opinion that the construction has been made either in violation of the plan sanctioned or devoid the sanction plan, then necessary steps shall be taken to deal with such unauthorized construction, in accordance with law.

The aforesaid respondent shall restrict the consideration of the representation with regard to unauthorized construction only and not enter into or decide any private dispute of the parties regarding right, title and interest in respect of the aforesaid land. It is made clear that this Court has not entered into the merits of the claim made by the petitioner and all points are left open to be decided by the aforesaid respondent at the time of consideration of the representation of the petitioner.

The petitioner is directed to forward a copy of the representation dated 25th November, 2019 to the

aforesaid respondent at the time of communicating the order of the Court.

W.P.A. 1766 of 2021 is disposed of.

Urgent photostat certified copy of this order be supplied to the parties, if applied for, as early as possible.

( Amrita Sinha, J.)