← Library
Calcutta High CourtCRR/300/2024disposed

Ashok Agarwal @ Ashok Kumar Agarwal v. State Of West Bengal And ORS.

2025-03-25Hon'Ble Justice Suvra Ghosh2 pages

March 25, 2025 217 ARDR CRR 277 of 2024 CRAN 1 of 2024 With CRR 278 of 2024 CRAN 1 of 2024 With CRR 279 of 2024 CRAN 1 of 2024 With CRR 280 of 2024 CRAN 1 of 2024 With CRR 281 of 2024 CRAN 1 of 2024 With CRR 282 of 2024 CRAN 1 of 2024 With CRR 284 of 2024 CRAN 1 of 2024 With CRR 286 of 2024 CRAN 1 of 2024 With CRR 287 of 2024 CRAN 1 of 2024 With CRR 288 of 2024 CRAN 1 of 2024 With CRR 293 of 2024 CRAN 1 of 2024 With CRR 295 of 2024 CRAN 1 of 2024 With CRR 296 of 2024 CRAN 1 of 2024 With CRR 298 of 2024 CRAN 1 of 2024 With CRR 299 of 2024 CRAN 1 of 2024 With CRR 300 of 2024 CRAN 1 of 2024 With CRR 302 of 2024 CRAN 1 of 2024 With CRR 304 of 2024 CRAN 1 of 2024 With

CRR 305 of 2024 CRAN 1 of 2024 Ashok Agarwal @ Ashok Kumar Agarwal Vs.

The State of West Bengal & ors.

Adv. Mrityunjoy Chatterjee, Adv. Manas Das, ...for the petitioner in all the matters.

The opposite parties are not represented.

Learned counsel for the petitioner in all the applications submits that the dues in connection with 17 cases have been cleared and the said cases have been disposed of by the learned trial Courts. Dues in connection with CRR 281 of 2024 and CRR 288 of 2024 are pending. In view of the above, this Court is inclined to hold that since nothing further remains to be adjudicated in the revisional applications, CRR 277 of 2024, CRR 278 of 2024, CRR 279 of 2024, CRR 280 of 2024, CRR 282 of 2024, CRR 284 of 2024, CRR 286 of 2024, CRR 287 of 2024, CRR 293 of 2024, CRR 295 of 2024, CRR 296 of 2024, CRR 298 of 2024, CRR 299 of 2024, CRR 300 of 2024, CRR 302 of 2024, CRR 304 of 2024 and CRR 305 of 2024 are disposed of. Since the interim order expires on 31st March, 2025, the said order be extended till 30th April, 2025 or until further orders, whichever is earlier insofar as CRR 281 of 2024 and CRR 288 of 2024 are concerned.

Let these matters appear under the same heading on 24th April, 2025.

Urgent certified website copy of this order, if applied for, be given to the parties, upon compliance of all requisite formalities. (Suvra Ghosh, J.)