Nimai Sarkar v. Wbsedcl And ORS.
14th March, (AK) W.P.A 4158 of 2023 Nimai Sarkar Vs.
The West Bengal State Electricity Distribution Company Limited and others Mr. Md. Kutubuddin ...for the petitioner.
Mr. Sumit Ray ...for the WBSEDCL.
An inspection report is filed by learned counsel for the WBSEDCL which indicates that at the present juncture there is an existing submersible pump at the locale and it is feasible to give electricity supply there. It is further submitted that a quotation has already been raised in that regard by the WBSEDCL.
Learned counsel for the petitioner submits that the quotation amount has already been deposited by the petitioner.
In such view of the matter, there is no further impediment to give an electricity connection to the petitioner for the purpose of running his submersible pump at the premises-in-question.
Accordingly, WPA 4158 of 2023 is disposed of by directing the WBSEDCL to give a new electricity connection to the petitioner at the premises as per the petitioner's application within a fortnight from date
subject to compliance of all due formalities by the petitioner.
There will be no order as to costs.
Urgent photostat copies of this order, if applied for, be given to the parties upon compliance of all requisite formalities.
(Sabyasachi Bhattacharyya, J.)