Gee Dee Mining Pvt Ltd And Another v. State Of West Bengal And ORS.
19.09.2022 rc/ct.no.10 Item No.111 WPA No. 9468 of 2022 Mr. Mir Awowar ...for the petitioners Mr. Soumitra Bandyopadhyay Mr. Aniruddha Sen ...for the State Mr. Sanjoy Saha Mr. S. Bhattacharjee for the WBMDTC Ltd.
Affidavit of service filed by the petitioners be taken on record.
It is submitted on behalf of the petitioners that being the highest bidder in e-auction for grant of mining lease held from November 07, 2016 to November 09,2016, the petitioners were granted mining lease which was executed and registered on 8th June, 2017. The term of the lease has expired on 7th June, 2022.
Due to Covid-19 pandemic and lockdown declared by the Government, the petitioners were unable to carry on mining operation for substantial period of time for which they have prayed for extension of the period of lease before the concerned authority.
Learned counsel draws the attention of the court to Clause 5 of part IX of the deed of lease which states that in the event of delay on the ground of force majeure the period of such delay shall be added to the period of lease. Learned counsel has also drawn the attention of this Court to the Memorandum dated 13th May, 2020 issued by the
Deputy Secretary, Government of India to the Secretaries of all Central Government Ministries/Departments which demonstrates that in view of the restrictions placed on the movement of goods, services and manpower on account of the lock down situation, dates for completion of contractual obligations which had to be completed on or after 20th February, 2020 shall stand extended for a period not less than three months and not more than six months. The petitioners submitted a representation before the concerned Authority on 2nd May, 2022 in this regard which is yet to be disposed by the Authority. The petitioners pray for a direction upon the Authority to consider the representation at the earliest.
It is submitted on behalf of the State respondents that the 2nd respondent be directed to consider the representation within a stipulated period of time. Upon consideration of the submissions made on behalf of the parties and material on record, the writ petition is disposed of directing the 2nd respondent to consider and dispose of the representation submitted by the petitioners dated 2nd May, 2022 within a period of one month from the date of communication of this order after taking into consideration the Memorandum dated 13th May, 2020 as well as clause 5 of part IX of the deed of lease and after affording reasonable opportunity of hearing to all the interested parties including the petitioners, in accordance with law.
The decision taken by the authority shall be communicated to the petitioners within a week thereafter. With the above directions, the writ petition being W.P.A. 9468 of 2022 is thus disposed of. However, there shall be no order as to costs.
Since no affidavit is invited, the allegations contained in the petition are deemed not to be admitted. Urgent certified website copy of this order, if applied for, be supplied to the parties upon compliance with all requisite formalities.
(Suvra Ghosh,J)