Ambud Buildcom Private Limited And ORS v. State Of West Bengal And ORS.
20.05.2025 W.P.A. 10540 of 2025 Item No.99 Ct. No.35 dc.
Ambud Buildcom Private Limited & Ors.
versus State of West Bengal & Ors.
Mr. Pranit Bag, Mr. Rahul Poddar, Mr. Anousko Das, Mr. Souvik Banerjee ... For the Petitioners.
Ms. Sonal Sinha, Ms. Ashmita Chakraborty, Mr. Sandipan Das ... For the State.
Affidavit-of-service filed in Court today be kept with the record.
Report submitted by the learned advocate appearing for the State be also kept with the record. A copy of the report be handed over to the learned advocate appearing for the petitioners.
The petitioners are aggrieved by the fact that in spite of permission being granted by the appropriate authorities, they are unable to carry out their construction work because of interference and/or obstruction created at the behest of the local miscreants.
State has submitted a report. The report contains the enquiry which was conducted by the Inspector-in-Charge, Rajarhat Police Station wherein it is admitted that proportionate area has already been converted into pond in respect of the area for which construction is being raised by the petitioners.
Having regard to the fact that the police authorities are having knowledge regarding the incidents which have been reported and for which the petitioners are also aggrieved, I am of the view that the police authorities would keep a surveillance and ensure that the petitioners be not obstructed and/or any untoward incident results because of continuation of work of the petitioners. With the aforesaid observations, the writ petition being WPA 10540 of 2025 is disposed of. There will be no order as to costs.
All concerned parties shall act on the server copy of this order duly downloaded from the official website of this Court.
Urgent photostat certified copy of this order, if applied for, be supplied to the parties upon compliance with all requisite formalities.
(Tirthankar Ghosh, J.)