Snehasish Mallick v. The Durgapur Projects Limited And ORS.
IN THE HIGH COURT AT CALCUTTA
CONSTITUTIONAL WRIT JURISDICTION APPELLATE SIDE 35 19.05.2025 PA Ct. no.2 WPA 10661 OF 2025 ------------- Snehasish Mallick Vs.
The Durgapur Projects Limited & Ors.
Mr. Siddhartha Sarkar, Adv.
....For the Petitioner Mr. Sujit Sankar Koley, Adv.
Mr. Swagatam Deb, Adv.
....For the Respondents Affidavit-of-service, filed in Court today, is taken on record.
Mr. Siddhartha Sarkar, learned Advocate appears for the petitioner.
Mr. Sujit Sankar Koley and Mr. Swagatam Deb learned Counsel appear for the respondents.
The father of the petitioner was an employee in Durgapur Projects Limited (in short DPL), the respondent no. 1. The petitioner's father retired from service on November 30, 2023. The petitioner has been paid the gratuity amount and leave salary to the tune of Rs.8,76,543/- on February 21, 2025. The petitioner, therefore, is entitled to interest for the delayed payment of principal amount of gratuity as per the provisions of Section 7(3A) of the Payment of Gratuity Act, 1972
(hereinafter referred to as the 1972 Act) and the interest for the delayed payment of leave salary computed on the basis of the petitioner's father last drawn pay since the same is part of the retiral benefits.
The issues involved in the instant writ petition are squarely covered by a recent judgment and order of this Court In the matter of : Kajal Pal -Vs.- The Durgapur Projects Ltd. & Ors. passed in WPA 11485 of 2021 on August 9, 2021. The consensus between the parties as was in case of Kajal Pal (supra) is also there in the instant case. As DPL, the employer has assured time bound payment, the rate of interest allowed is less than the present rate under the 1972 Act.
This writ petition as such, is disposed of on the similar lines as in Kajal Pal (supra), which are as follows:- The respondent no. 1 is directed to pay the interest on the principal amount of gratuity and leave salary of Rs.8,76,543/- @ 6% per annum within a period of six months from the date of communication of a server copy of this order without insisting upon production of a certified copy thereof and, in default, statutory rate of interest @10% per annum as in case of gratuity and leave salary will be attracted on the entire amount from December 01, 2023 till February 21, 2025.
Nothing further remains to be adjudicated in this writ petition.
Since affidavits are not called for, the allegations made in the writ petition are deemed not to have been admitted by the respondents.
Accordingly, WPA 10661 of 2025 stands disposed of.
Parties shall act on the website copy of this order duly downloaded from the official website of this Hon'ble Court.
(Aniruddha Roy, J.)