Mrityun Das @ Mrityunjoy Das v. The West Bengal State Electricity Distribution Company Limited And ORS.
22.07.2025 Sl No.39 Ct. No.15 S.A.
WPA 14607 of 2025 Mrityun Das @ Mrityunjoy Das -vsWest Bengal State Electricity Distribution Company Limited & Ors.
Mr. Usof Ali Dewan Mr. Arup Sarkar Ms. Shibani Agarwal ...for the petitioner Mr. Debjit Mukherjee ...for WBSEDCL The petitioner seeks electricity connection for his submersible pump set.
Learned advocate appearing for West Bengal State Electricity Distribution Company Limited (WBSEDCL) submits that such connection shall be given within a period of two months from date. In view of the aforesaid, nothing further remains to be decided in this writ petition.
Accordingly, this writ petition is disposed of giving a direction upon WBSEDCL to effect the connection to the submersible pump set of the petitioner within a period of eight weeks from date. Accordingly, WPA 14607 of 2025 stands disposed of.
Let the instruction filed by WBSEDCL be kept with the record.
Urgent photostat certified copy of this order, if applied for, be supplied to the learned advocates for the parties on usual undertakings.
(Kausik Chanda, J.)