Calcutta High CourtWPA/17152/2024disposed
Mosiulla Biswas v. Wbsedcl And ANR
2024-08-05Hon'Ble Justice Shampa Sarkar1 pages
Item No.94 05.08.2024 Court. No. 9 GB W.P.A. 17152 of 2024 Mosiulla Biswas Vs.
The West Bengal State Electricity Distribution Company Limited & Ors.
Mr. Indranil Halder ... for the Petitioner.
Mr. Supriyo Chattopadhyay ... for the WBSEDCL.
Upon cessation of the monsoon season, connection will be granted to the petitioner, as ensured by the West Bengal State Electricity Distribution Company Limited, before October 9, 2024, that is, before the Durga Puja commences. The time period mentioned is peremptory.
Accordingly, writ petition is disposed of.
However, there will be no order as to costs.
Parties are directed to act on the basis of the server copy of this order.
(Shampa Sarkar, J.)