Chanmuni Hemram v. The West Bengal State Electricity Distribution Company Limited And ORS.
WPA 20415 of 2025 Chanmuni Hemram Vs.
The West Bengal State Electricity Distribution Company Limited & Ors. Md. Kutubuddin ...for the Petitioner Mr. Sujit Sankar Koley ...for WBSEDCL The petitioner seeks an electricity connection for 04-09-2025 AKG Ct. 15 his submersible pump set.
The learned counsel appearing for West Bengal State Electricity Distribution Company Limited (WBSEDCL) submits that an inspection is required to be conducted, after which a decision regarding the connection will be made.
In light of the foregoing, there is no necessity to keep this writ petition pending.
Considering the ongoing monsoon season, it is hereby directed that WBSEDCL shall conduct the inspection within one month from the date of this order. Based on the findings of the inspection, the petitioner's application for the electricity connection shall be duly considered within two months thereafter. Accordingly, WPA 20415 of 2025 is disposed of. Urgent certified website copies of this order, if applied for, be made available to the parties upon compliance with the requisite formalities.
(Kausik Chanda, J.)