Gramim Majdur Unnayan Co Op Labour Contract And Construction Society Ltd v. The Executive Engineer, Malda Irrigation Department And ORS.
WPA 23396 OF 2023 05.10.2023 Gramin Majdur Unnayan Co Op Labour Contract and Construction Society Ltd.
Sl no.16 Ct no. 2 - Vs - P.M.
The Executive Engineer, Malda Irrigation Department & Ors.
Mr. Sandip Choraria ... for the petitioner Mr. Anirban Ray, Ld. Govt. Pleader Md. T. M. Siddiqui, Mr. T. Chakraborty, Mr. S. Sanyal.
... for the State Heard learned advocates appearing for the parties.
Petitioner has filed this writ petition for considering of its claim for reimbursement of the differential amount of tax due to change in the rate of tax with effect from 18th July, 2022 along with payment of statutory interest.
From record I find that for redressal of the grievance raised in this writ petition, petitioner has made a representation before the respondent authority concerned on 24th August, 2023 being annexure P/6 to the writ petition.
Considering the facts and circumstances of this case and submission of the parties this writ
petition being WPA 23396 of 2023 is disposed of by directing the respondent authority concerned to consider and dispose of the aforesaid representation of the petitioner in accordance with law and by passing a reasoned and speaking order after giving opportunity of hearing to the petitioner or its authorized representatives within a period of four weeks from the date of communication of this order. It is clarified that this Court has not gone into the merits of the aforesaid representation and the authority concerned will consider the same strictly in accordance with law.
(Md. Nizamuddin, J.)