← Library
Calcutta High CourtCPAN/1387/2022disposed

Bindu Bhusan Dey And ORS. v. Sudipta Rong And ANR.

2023-03-02Hon'Ble Justice Sabyasachi Bhattacharyya3 pages

AD-06&07 Ct No.09 02.03.2023 TN CPAN 1387 of 2022 In WPA No. 12089 of 2022 Bindu Bhusan Dey and others Vs.

Mr. Sudipta Rong and another Mr. Sk. Sahjahan Ali .... for the applicants/petitioners Mr. P. Das .... for the alleged contemnors Learned counsel for the petitioners contends that despite the specific direction of the court dated July 06, 2022 passed in WPA No. 12089 of 2022 to the effect that the alleged contemnor no.2/writ petitioner was to be given a new electricity connection for the purpose of running his saw-mill, subject to the alleged contemnor no.2 complying with all formalities as contemplated for getting such connection and also subject to the petitioner having valid permit/licence, if required by any other Statute than the 2003 Act, for the purpose of running such saw-mill, the connection was given to the alleged contemnor no. 2 without the alleged contemnor having complied with all formalities inasmuch as the permit/licence sought to be relied on by the alleged contemnor was not valid in the eye of law.

It is submitted that the concerned authorities under the relevant Act subsequently passed an order for disconnection of the electricity due to such illegality having been committed by the alleged contemnor. It is submitted that thus, the entire process of giving electricity connection to the alleged contemnor was vitiated by a deliberate and willful contravention of the direction of this court. Learned counsel appearing for the alleged contemnors submits that there was a bona fide misinterpretation of the order of this court inasmuch as the Station Manager-in-question was under the impression that the alleged contemnor no. 2 had complied with all formalities, even required by the other statute regarding having a valid permit/licence.

It is seen from the materials on record that apparently a so-called permit was furnished by the alleged contemnor for the purpose of obtaining electricity connection, which was subsequently held to be invalid in law. As such, it cannot be said that at the relevant juncture, the alleged contemnors were guilty of deliberate contravention of the order of this court.

penal measures for contempt of court need not be imposed on the alleged contemnors.

Moreover, it is submitted that subsequently the electricity supply has already been disconnected by the WBSEDCL authorities.

In such view of the matter, CPAN 1387 of 2022 is disposed of without any order as to costs. Urgent photostat certified copies of this order, if applied for, be made available to the parties upon compliance with the requisite formalities.

(Sabyasachi Bhattacharyya, J.)