M/S. Arcon Project Pvt. Ltd. v. Bridge And Roof Co.(India) Ltd. And ORS.
19.12.2025 (D/L-09) Ct. No.25 (B.K.N.) W.P.A. 29896 of 2024 M/s. Arcon Project Private Limited Vs.
Bridge and Roof Co. (India) Ltd. & Ors.
Ms. Rupsa Sreemani, Mr. Debdut Banerjee ... for the Petitioner Mr. Debangshu Biswas ... for the Respondent No. 1
1. The matter is listed under the heading "To Be Mentioned" on the prayer made by the learned counsel for the petitioner. Counsel for the petitioner submits that he has received an written instruction from the petitioner stating that the parties have amicably settled the matter and the petitioner does not want to proceed with the matter.
2. Let the communication dated 9th December, 2025 be kept with the record.
3. Considering the communication dated 9th December, 2025 and the submission made by the petitioner, W.P.A. 29896 of 2024 is dismissed as withdrawn.
4. Interim order, if any, stands vacated.
(Krishna Rao, J.)