The Braithwaite Burn And Jessop Construction Co. Ltd. v. General Manager, Eastern Railway
OD 4 ORDER SHEET AP/5/2025
IN THE HIGH COURT AT CALCUTTA
ORDINARY ORIGINAL CIVIL JURISDICTION ORIGINAL SIDE THE BRAITHWAITE BURN AND JESSOP CONSTRUCTION CO. LTD. VS GENERAL MANAGER, EASTERN RAILWAY
BEFORE:
The Hon'ble JUSTICE SHAMPA SARKAR Date: 22nd January, 2025.
Appearance:
Mr. Sanjib Kumar Mal, Adv.
Mr. Atanu Roychaudhuri, Adv.
Mr. Pushan Majumdar, Adv.
...for the petitioner Ms. Aparna Banerjee, Adv.
...for the respondent The Court: This is an application for extension of the mandate of the learned Arbitrator. The mandate of the learned Arbitrator expired on 15th January, 2025. This application for extension of mandate has been filed by the claimant on 13th January, 2025. It is submitted that arguments are over. Ms. Banerjee, learned advocate for the respondent does not deny the above fact.
Under such circumstances, the application is disposed of by extending the mandate of the learned Arbitrator by a further period of six months from the date of communication of this order.
This order is passed for the ends of justice as all that remains to be done by the learned Arbitrator is to publish the award. (SHAMPA SARKAR, J.) B.Pal