Srei Equipment Finance Limited v. Mep Infrastructure Developers Limited
OD-27 ORDER SHEET AP/28/2020
IN THE HIGH COURT AT CALCUTTA
Ordinary Original Civil Jurisdiction ORIGINAL SIDE SREI EQUIPMENT FINANCE LIMITED VS MEP INFRASTRUCTURE DEVELOPERS LIMITED
BEFORE:
The Hon'ble JUSTICE SHEKHAR B. SARAF Date : 27th September, 2022 Appearance:
Mr. Saubhik Chowdhury, Adv.
Ms. Tapasika Bose, Adv.
...for the petitioner Mr. Sagnik Basu, Adv.
Mr. Mainak Biswas, Adv.
...for the respondent The Court: Heard Counsel appearing on behalf of the parties. An interim order was passed in this matter on 12th March, 2020. This order is now subsisting for over two years. In light of the same, parties are directed to take steps in accordance with law for proceeding with arbitration immediately.
The interim order passed shall continue for a further period of four weeks or until further orders passed by the Tribunal, whichever is earlier. AP/28/2020 is, accordingly, disposed of.
(SHEKHAR B. SARAF, J.) R.Bhar