Exide Industries Limited v. West Bengal Renewable Energy Development Agency
ODC-13
IN THE HIGH COURT AT CALCUTTA
ORDINARY ORIGINAL CIVIL JURISDICTION ORIGINAL SIDE [COMMERCIAL DIVISION] AP-COM/525/2024 Exide Industries Limited VS West Bengal Renewable Energy Development Agency
BEFORE:
The Hon'ble JUSTICE RAVI KRISHAN KAPUR Date : 2nd May, 2024.
Appearance:
Mr. Ratnanko Banerji, Sr. Adv.
Mr. Arik Banerjee, Adv.
Mr. Jaydeb Ghorai, Adv.
Mr. Suman Chatterjee, Adv.
Mr. Diptesh Ghorai, Adv.
...for petitioner.
Mr. Sirsanya Bandopadhyay, Adv.
Mr. Sohom Kr. Roy, Adv.
Mr. Arka Kr. Nag, Adv.
...for respondent.
The Court: This is an application filed under Section 29A of the Arbitration and Conciliation Act, 1996. It is submitted on behalf of the parties that for unavoidable reasons the Arbitral Tribunal has been unable to conclude the proceedings.
The respondent is represented and does not object to the prayer for extension.
I have considered the averments in this application and I am satisfied that there are sufficient grounds and good cause as to why the Arbitral Tribunal was unable to conclude the arbitral proceedings.
In such circumstances, by consent of the parties, AP-COM/525/2024 stands allowed by extending the mandate of the Arbitrator by a further of period of six months from the date of passing of this order. With the aforesaid directions, AP-COM/525/2024 stands disposed of. (RAVI KRISHAN KAPUR, J.) SK.