Re : Shaping Dreams Projects Pvt Ltd And v. Divyajyoti Sponge Iron Pvt Ltd
OD-10
IN THE HIGH COURT AT CALCUTTA
Original Jurisdiction ORIGINAL SIDE CP/456/2016 RE : SHAPING DREAMS PROJECTS PVT LTD AND VS DIVYAJYOTI SPONGE IRON PVT LTD
BEFORE:
The Hon'ble JUSTICE RAVI KRISHAN KAPUR Date : 23rd February, 2023 The Court :- None appears on behalf of the petitioning creditor nor is any accommodation prayed for on their behalf.
The company is represented and submits that this proceeding is at a "preadmission stage". I find from the earlier orders of Court that save and except direction for affidavits, no other steps have been taken in this proceeding. This proceeding is pending since 2016.
In view of the amended provisions of the Companies Act, 2013 and the decisions in Action Ispat and Power Private Limited-versus-Shyam Metalics and Energy Limited reported in (2021) 2 SCC 641 and in A. Navinchandra Steels Private Limited -versus- Srei Equipment Finance Limited and Others reported in AIR 2021 SC 1180, in my view this Court does not have any jurisdiction to entertain this matter. There is no irreversible situation which has arisen warranting this Court retaining this proceeding. In view of the aforesaid, CP/456/2016 stands transferred to the National Company Law Tribunal, Kolkata.
The Department shall treat CP/456/2016 as disposed of insofar as the records of this Court are concerned.
It is needless to mention that any connected application is also transferred to the National Company Law Tribunal, Kolkata. (RAVI KRISHAN KAPUR, J.) S.Bag