OCD -11 ORDER SHEET

IN THE HIGH COURT AT CALCUTTA

COMMERCIAL DIVISION ORIGINAL SIDE AP-COM/671/2025 M/S ZILLION INFRAPROJECTS PVT LTD(CURRENTLY UNDER CIRP) VS BRIDGE AND ROOF CO (INDIA) LTD

BEFORE:

The Hon'ble JUSTICE SHAMPA SARKAR Date: 27th August, 2025.

Appearance:

Mr. Soumen Das, Adv.

Mr. Ajaya Choudhury, Adv.

Mr. Altamas Alim, Adv.

.... for the petitioner Mr. Amit Meharia, Adv.

Ms. Paromita Banerjee, Adv.

Mr. Rohan Raj, Adv.

...for the respondent.

The Court: This is an application for extension of the mandate of the learned arbitrator, which expired on July, 11, 2025. It is submitted by both the parties that the arbitral proceeding is at the stage of arguments. This Court is of the view that sufficient progress has been made in the arbitration proceedings and the same is near completion.

For the ends of justice, the mandate of the learned arbitrator is extended by a further period of one year from the date of communication of this order, to enable the learned arbitrator to make and publish his award.

AP-COM 671 of 2025 is disposed of accordingly. (SHAMPA SARKAR, J.) TR/