Smti.G.Desamma v. The Superintending Engineer And ANR
IN THE HIGH COURT AT CALCUTTA
[ CIRCUIT BENCH AT PORT BLAIR ] *** WPA/27/2025 Smt G. Desamma Vs.
The Superintending Engineer and others Mr. U.Partha Sarathi ... for the petitioner Mr. S.C. Mishra ... for the respondents January 20, 2025 [SR] Item no. 11 1.
The petitioner's application seeking new electricity connection is pending consideration before the electricity department. The petitioner prays for consideration of the said application.
2.
Learned advocate representing the department submits, upon instructions, that the petitioner is already enjoying electricity from a meter at the same premises. 3.
The department is directed to consider the application and communicate to the petitioner, the fate of her application at the earliest.
4.
If the department is of the opinion that the new connection can be given to the petitioner then, the same shall be accorded in accordance with law subject to compliance of all statutory formalities.
5.
The fate of the petitioner's application shall be communicated to the petitioner at the earliest but positively
within a period of four weeks from the date of communication of this order.
6.
The writ petition stands disposed of. No order as to costs. ( Madhuresh Prasad, J. )