Ujjwal Roy v. The Superintending Engineer And Another
IN THE HIGH COURT AT CALCUTTA
[CIRCUIT BENCH AT PORT BLAIR] *** WPA/101/2026 Ujjwal Roy Vs.
The Superintending Engineer and another Mr. K.Mohammed Sheheer ... for the petitioner Mr. S.C.Mishra ... for the respondents April 24, 2026 [AKB] Item No.9 Learned counsel for the respondent authorities has placed a copy of the letter dated 20.03.2026, let the same be kept with the record.
The learned counsel appearing for the petitioner submits that the grievance made in the writ petition has already been redressed, since the Licensing Authority has already provided the electricity connection on 20.03.2026.
In view of the letter of communication dated 20.03.2026 placed on record, the writ petition is disposed of as having become infructuous.
(Smita Das De, J.)