The Collector Of Stamps (Enforcement-2), Mumbai v. Unity Realty And Developers Ltd. (Urdl) And ORS
Board Sr.No.:-17
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
APPELLATE SIDE CIVIL JURISDICTION WRIT PETITION NO. 971 OF 2016 Unity Realty And Developers Ltd. (urdl) ....PETITIONER V/S State Of Maharashtra Throug Principal Secretary (revenue) Dept. Of Revenue And Forest And Ors.
....RESPONDENT WITH INTERIM APPLICATION NO. 13336 OF 2025 In Writ Petition 971 OF 2016 The Collector Of Stamps (enforcement-2), Mumbai ....PETITIONER V/S Unity Realty And Developers Ltd. (urdl) And Ors ....RESPONDENT WITH CIVIL APPLICATION IN WP NO. 373 OF 2016 In Writ Petition 971 OF 2016 Unity Realty And Developers Ltd. (urdl) ....APPLICANT V/S State Of Maharashtra Throug Principal Secretary (revenue) Dept. Of Revenue And Forest And Ors.
....RESPONDENT Page 1/2
Mr. Sanjiv Punalekar for Petitioner.
Mrs. Sulbha Chipade, AGP for State-Respondent CORAM :
HON'BLE MS. JUSTICE GAURI GODSE J DATE :
9th April, 2026 P.C. :
At the request of learned counsel for the Respondent, Stand over to 10/06/2026 If any ad-interim / interim relief is operating till today, the same shall continue to operate till the next date. If ad-interim/ interim relief is granted not for a limited period, the same shall remain unaffected.