Nagnechi Construction Pvt. Ltd. v. Hella Infra Market Ltd. And 4 ORS
19-ARBP-78-2024 @ IAL-33895-2022 copy.docx
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
PURTI PRASAD PARAB ORDINARY ORIGINAL CIVIL JURISDICTION PURTI PRASAD PARAB Date: 2025.06.17 13:09:01 +0530 ARBITRATION PETITION NO. 78 OF 2024 ALONGWITH INTERIM APPLICATION (L) NO. 33895 OF 2022 IN ARBITRATION PETITION NO. 78 OF 2024 Nagnechi Construction Pvt. Ltd.
...Petitioner
Versus
Hella Infra Market Ltd. and Ors.
...Respondents
None for the Petitioner.
Mr. Amrut Joshi i/b Mr. Shivraj Patne & Mr. Shon Gadgil for the Respondent.
CORAM
: SOMASEKHAR SUNDARESAN, J.
DATE : JUNE 9, 2025 PC :
1.
Learned Counsel for the Respondent submits that the delay in the matter was already condoned by an order dated April 15, 2025 and the matter was scheduled to come up on June 17, 2025. However, he submits that the condonation appears to have been granted by this Court on account of a mis-statement made to this Court on behalf of the Petitioner. Liberty to point out the same when the matter is called out on June 17, 2025. Both the parties would be heard on that date.
2.
All actions required to be taken pursuant to this order shall be taken upon receipt of a downloaded copy as available on this Court's website.
[ SOMASEKHAR SUNDARESAN, J.] June 9, 2025 Purti Parab