Topworth Infra Pvt Ltd(Tipl) v. Dilip Buildcon Ltd(Dbl)
5-CARBP-15-24.doc Sharayu Khot.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION COMMERCIAL ARBITRATION PETITION NO. 15 OF 2024 Topworth Infra Pvt. Ltd. (TIPL)
...Petitioner
Versus
Dilip Buildcon Ltd. (DBL)
...Respondent
---------- Mr. Sandeep Bajaj, Mr. Anuj Jhaveri, Mr. Devansh Jain a/w Mr. Mihir Modi i/b Mihir Modi for the Petitioner.
Ms. Nandita Dethe a/w Ms. Dhara Modi i/b Singhania Legal Services of Respondent.
---------- CORAM : R.I. CHAGLA J DATE : 4 March 2024 ORDER :
1.
The learned Advocate appearing for the Respondent has sought time to file Vakalatnama in the matter. Vakalatnama on behalf of the Respondent shall be filed within a period of one week from the SHARAYU PANDURANG KHOT date of this order.
Digitally signed by SHARAYU PANDURANG KHOT Date:
2024.03.04 18:30:38 +0530 2.
The learned Advocate appearing for the Petitioner has submitted that through inadvertence Schedule to the Concession 1/2
5-CARBP-15-24.doc Agreement, which forms part of the Concession Agreement, remained to be annexed at Exh.C to the Arbitration Petition. 3.
In view thereof, the Petitioner shall carry out the amendment to Exh.C by incorporating the Schedule to the Concession Agreement, which was part of the record of the learned Arbitrator and the same shall be done within a period of one week from the date of this order. Re-verification is dispensed with. 4.
The Commercial Arbitration Petition shall be placed on 18th March 2024.
[R.I. CHAGLA J.] 2/2