Abdulla Mehmood Palla v. Hemlata Investment Pvt. Ltd.(Mp) And Pratibha Shipping Company Ltd.(Mr)
2025:BHC-OS:12396 27 ia2160-24
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORIGINAL ORDINARY APPELLATE JURISDICTION INTERIM APPLICATION NO. 2160 OF 2024 IN COMPANY PETITION NO. 265 OF 2014 Abdulla Mehmood Palla In the matter betwen:
... Applicant.
Hemlata Investment Pvt. Ltd.
... Petitioner.
Versus
Pratibha Shipping Company Ltd. represent by Official Liquidator ... Respondent.
----- Mr.Rupesh R. Langekar i/by Kunal Gaikwad for the Applicant. Mr. Sneha Goyal, for Official Liquidator Mr. Satyajit Raul, Official Liquidator present Mr.Chetan Shelke, Deputy Official Liquidator present. ----- Coram : Sharmila U. Deshmukh, J.
Date : July 31, 2025 P.C. :
1.
Interim Application seeks condonation of delay of 543 days caused in filing the affidavit of proof of debt with the Official Liquidator. Learned counsel appearing for the Official Liquidator fairly does not oppose the application.
2.
For the reasons stated in the application, the delay of 543 days is condoned. The Official Liquidator is directed to adjudicate the claim of the Applicant on its own merits and in accordance with law. 3.
Interim Application is allowed in above terms. [Sharmila U. Deshmukh, J.] sa_mandawgad 1 of Signed by: Sanjay A. Mandawgad Designation: PA To Honourable Judge Date: 01/08/2025 18:17:16