1.
This is a Petition filed under Section 37 of the Arbitration and Conciliation Act, 1996 ("the Act").
2.
Heard Learned Counsel for the parties for an overview of the matter. Based on the nature of the issues involved and bearing in mind the scope of jurisdiction under Section 37 of the Act, Learned Counsel have graciously agreed that the Appellant shall take not more than 15 minutes and the Respondents shall take no longer than 15 minutes for verbal arguments in the matter.
Digitally signed by AARTI GAJANAN PALKAR Date:
2025.04.09 16:24:44 +0530 AARTI GAJANAN PALKAR APRIL 2, 2025 Aarti Palkar
917.ARA.7.2025.doc 3.
Towards this end, the parties shall file a short Note on Submissions, not exceeding five pages, along with page and case law references, focusing on the scope of Section 37 of the Act, and setting out the manner in which the points canvassed by them ought to be accepted by this Court.
4.
It is made clear that the time commitments made above shall bind the parties, and such time shall be utilized at the discretion of the Counsel for verbalizing the pivotal submissions, resting assured that the rest of their contentions from their Note on Submissions, would be dealt with by the Court.
5.
With the aforesaid commitments, stand over to April 9, 2025 on Production Board, for "Final Hearing and Disposal". 6.
All actions required to be taken pursuant to this order, shall be taken upon receipt of a downloaded copy as available on this Court's website.
[ SOMASEKHAR SUNDARESAN, J.] APRIL 2, 2025 Aarti Palkar