Dhirendra Phadte And 4 ORS v. Tarun Radhakrishin Tahilani And 8 ORS
PILWP 3 of 2024 Andreza
IN THE HIGH COURT OF BOMBAY AT GOA
PUBLIC INTEREST LITIGATION WP NO.3 OF 2024 WITH PUBLIC INTEREST LITIGATION WP NO.4 OF 2024 PUBLIC INTEREST LITIGATION WP NO.3 OF 2024 DHIRENDRA PHADTE AND 4 ORS ... PETITIONERS
Versus
TARUN RADHAKRISHIN TAHILANI AND 8 ORS ... RESPONDENTS WITH PUBLIC INTEREST LITIGATION WP NO.4 OF 2024 ANAND ESVONTA ACHORENCAR AND ANR ... PETITIONERS
Versus
STATE OF GOA, THR. ITS CHIEF SECRETARY AND 4 ORS., ... RESPONDENTS Mr Richard Almeida and Mr Samuel Abraham, Advocates for the Petitioners.
Mr. Y. V. Nadkarni, Advocate with Mr. Nilay Naik, Advocate for the Petitioner in PILWP N0. 4 of 2024.
Mr Raunaq Rao, Advocate with Ms. Tabitha Souto, Advocate for Respondent No.1 in PILWP No. 3/2024 and Respondent no. 5 in PILWP No. 4 of 2024.
Mr P. Arolkar, Additional Government Advocate for the respondent Nos 2 to 4, 6, 7 and 9 in PILWP No.3 of 2024. Ms Maria Correia, Additional Government Advocate for respondent No.8 in PILWP No.3 of 2024.
Mr Prayash Shirodkar, Advocate for respondent No.5 in PILWP No.3 of 2024 and for respondent No.4 in PILWP No.4 of 2024. Mr D. Pangam, Advocate General with Mr P. Arolkar and Ms. Maria Correia, Additional Government Advocate for the Respondent Nos. 2 to 4, 6, 7 and 9.
Mr P. Shirodkar, Advocate for Respondent No.5. Mr. Pravin Faldessai, Additional Government Advocate for Respondent nos. 1 to 3 in PILWP No. 4 of 2024.. CORAM:- BHARATI H. DANGRE & NIVEDITA P. MEHTA, JJ.
DATED :- 26th March, 2025 26th March, 2025
PILWP 3 of 2024 P.C.
We are informed that during the pendency of the two Public Interest Litigation, which raise an objection to the alleged construction undertaken by Respondent nos. 1 and 5 in Salvador do Mundo Village Bardez Taluka, show cause notice was issued on the basis of the complaints filed before the office of the Deputy Town Planner. The proceedings were followed up before the Senior Town Planner in which even the Public Interest Litigation Petitioners were heard. It is informed that the Deputy Town Planner on 10.01.2025 has passed an Order in relation to the proposed construction of the residential house (as per the revised plan) and has approved the plan and granted permission for the construction of the residential house, staff quarters, swimming pool and compound wall by recording that if falls within the Settlement Zone of Regional Plan 2021 and beyond the High Tide Line.
2. In the wake of the aforesaid Order, the Petition came to be amended and the respective Counsel for Respondent nos. 1 and 5 in the two PIL Petitions are desirous to place on record their additional affidavit. In addition, we also expect a response from the office of the Town Planner so as to justify the passing of the Order dated 10.01.2025.
3. Re-notify to 09.04.2025.
NIVEDITA P. MEHTA, J.
BHARATI H. DANGRE, J.
Signed by: ANDREZA RODRIGUES EPEREIRA Designation: Senior Private Secretary to the Hon'ble Judge Date: 27/03/2025 16:13:14 26th March, 2025