Shri. Laxman Rambhau Bhandare And ANR. v. Union Of India Through The General Manager, Mumbai
31. IA 7998-2024.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO. 7998 OF 2024 IN FIRST APPEAL (ST) NO. 24736 OF 2022 ANAND SUDHAKAR SUDAME Laxman Rambhau Bhandare & anr.
..Applicants
Versus
Union of India through the General Manager, Central ..Respondent Railway, Mumbai by ANAND SUDHAKAR SUDAME Date:
2026.01.30 18:28:52 +0530 Mr. Mohan Rao, Advocate, for the Applicants Mr. T. J. Pandian, Advocate, for the Respondent CORAM : RAJESH S. PATIL, J.
DATE : 27.01.2026 P. C.
1.
This Interim Application is filed seeking condonation of delay of 33 days in filing the First Appeal.
2.
The First Appeal is arising out of the impugned Order dated 27.05.2022 passed by the Railway Claims Tribunal. 3.
Mr. Pandian, learned Counsel who is on the panel of the Railways is present in Court. Hence, this Court has requested him to appear in the present proceeding.
4.
Heard learned Counsel for the parties. I have gone through the contents of the Application.
5.
A case is made out to allow the Interim Application. Anand
31. IA 7998-2024.doc 6.
The Interim Application stands allowed in terms of prayer clause (a).
7.
Mr. Rao, learned Counsel is hereby directed to file a compilation of documents by 20.02.2026.
8.
Since the Appeal is of the year 2022, the Appeal be listed on 24.02.2026.
(RAJESH S. PATIL, J.) Anand