The Executive Engineer, Raigad v. Alisab Ibrahim Mahaldar And ORS.
61-IA-8939-2024.DOC
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO. 8939 OF 2024 (for condonation of delay) IN FIRST APPEAL (ST.) NO. 13810 OF 2023 The Executive Engineer, Hetavane Dam Division, Kolad, Dist. Raigad.
Digitally signed by SHRADDHA KAMLESH TALEKAR Date:
2024.09.21 11:27:53 +0530 ... Applicant/ Appellant SHRADDHA KAMLESH TALEKAR
Versus
1. Alisab Ibarahim Mahaldar & 2 Ors.
...Respondents
Ms. Chaitrali Deshmukh for Applicant/ Appellant Mr. A.R. Patil, Addl. G.P. for the State-Respondent Nos. 2 & 3. _______________________
CORAM:
SOMASEKHAR SUNDARESAN, J.
Date :
September 13, 2024 _______________________ P.C.
1.
Since this application is coming up for the first time, issue notice to the Respondents, returnable on November 14, 2024. Hamdast permitted. 2.
In addition, the Applicant is permitted to issue private notice by all permissible modes of service, and to file an affidavit of service, with tangible evidence of service, on or before the next date. 3.
Learned Addl. GP waives service for Respondent Nos. 2 and 3. 4.
Stand over to November 14, 2024.
September 13, 2024 Shraddha Talekar PS
61-IA-8939-2024.DOC 5.
Assistant of this Court. All concerned will act on production by fax or email (SOMASEKHAR SUNDARESAN, J.) September 13, 2024 Shraddha Talekar PS