The Executive Engineer, Raigad v. Parvati Shankar Baikar And ORS.
6.IA.9865.2024.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO.9865 OF 2024 IN FIRST APPEAL (STAMP) NO.18931 OF 2023 WITH INTERIM APPLICATION NO.9866 OF 2024 IN FIRST APPEAL (STAMP) NO.18931 OF 2023 The Executive Engineer, Raigad ....
Applicant Vs.
Parvati Shankar Baikar & Ors.
....
Respondents _________ Ms. Chaitrali A. Deshmukh for Applicant / Appellant. _________
CORAM
: SOMASEKHAR SUNDARESAN, J.
DATE : 09 AUGUST, 2024 P. C.
1.
Heard the Learned Counsel for the Applicant. The matter at hand involves dealing with a prayer for condonation of delay of over six years in a challenge to a judgment dated 15th April, 2017 passed by the Learned Civil Judge Senior Division, Mahad. The judgment was rendered in Land Reference No.23 of 2006. 2.
The reasons cited in the Application do not inspire confidence. They essentially relate to internal bureaucratic process delays on the part of the Applicant.
Digitally signed by ASHWINI JANARDAN VALLAKATI Date:
2024.08.09 17:56:35 +0530 ASHWINI JANARDAN VALLAKATI 3.
Upon a review of the record and after hearing the Counsel, the Application seeking condonation of delay, is hereby rejected in 09 August, 2024
6.IA.9865.2024.doc the absence of any sufficient cause being shown. Consequently, other connected Applications too are disposed of as not being necessary to be adjudicated.
4.
This order will be digitally signed by the Private Secretary/Personal Assistant of this Court. All concerned will act order.
[SOMASEKHAR SUNDARESAN, J.] 09 August, 2024