← Library
Bombay High CourtS/148/2024disposed off

Sameera Swapan Biswas v. Saroj Sorab Engineer

2025-11-06Hon'Ble Shri Justice R. I. Chagla1 pages

26-s-148-2024.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION SUIT NO.148 OF 2024 WITH INTERIM APPLICATION NO.1416 OF 2024 IN SUIT NO.148 OF 2024 Sameera Swapan Biswas ..

Plaintiff.

v/s.

Saroj Sorab Engineer & Others ..

Defendants.

by SMITA RAJNIKANT JOSHI Date:

2025.11.07 09:55:17 +0530 SMITA RAJNIKANT JOSHI Adv. Alisha Lambay i/b. Lambay & Co., for the Plaintiff. Adv. M. B. Madekar, for Defendant Nos. 1 to 3. CORAM: FIRDOSH P. POONIWALLA,J.

DATE : 6th NOVEMBER, 2025.

P. C:- Mentioned. Taken out of turn.

The time granted for making payment to the Plaintiff by Defendant Nos. 1 to 3 as per the two Minutes of Order, as recorded in the Order dated 22nd August, 2025 of R. I. Chagla, J. is extended till 27th November, 2025.

Stand over to 27th November, 2025.

(FIRDOSH P. POONIWALLA,J.) S.R.JOSHI