← Library
Bombay High CourtARBAP/13/2024disposed off

Goverdhangiri Co Operative Housing Society Ltd v. Bharat Infrastructure And Engineering Limited And ANR

2025-02-24Hon'Ble Shri Justice Somasekhar Sundaresan1 pages

955-ARBAP-13-2024 copy.docx

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

PURTI PRASAD PARAB ORDINARY ORIGINAL CIVIL JURISDICTION PURTI PRASAD PARAB Date: 2025.02.26 12:44:57 +0530 ARBITRATION APPLICATION NO. 13 OF 2024 Govardhangiri Co-operative Housing Society Ltd.

...Applicant

Versus

Bharat Infrastructure And Engineering Limited and Anr.

...Respondents

Mr. Vikramjit Singh Garewal a/w Ms. Meghna Mehta i/b M/s. Shah & Sanghavi for the Applicant.

CORAM

: SOMASEKHAR SUNDARESAN, J.

DATE : FEBRUARY 24, 2025 PC :

1.

Since the matter is coming up after a significant gap of time, to enable the Applicant to apprise this Court about specific facts of the case, list under the caption "Post Notice Matters" on March 3, 2025. 2.

All actions required to be taken pursuant to this order shall be taken upon receipt of a downloaded copy as available on this Court's website.

[ SOMASEKHAR SUNDARESAN, J.] February 24, 2025