Santosh R Dubey v. The State Of Maharashtra Through Chief Secretary State Of Maharashtra
by JYOTI PRAKASH PAWAR Date: 2025.03.27 14:11:17 +0530 JYOTI PRAKASH PAWAR JPP 19. WP 920.2024.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION WRIT PETITION NO. 920 OF 2024 Santosh R. Dubey ... Petitioner V/s.
State of Maharashtra through Chief Secretary and Ors.
... Respondents _______________________________________ Mr. Santosh R. Dubey, Petitioner-in-person Mr. S.R. Nargolkar (through V.C.) with Ms. Neeta Patil and Mr. Sanket Chandane for Respondent No.2 Ms. Oorja Dhond i/b. Ms. Komal R. Punjabi for Respondent No.4 - BMC Ms. P.H. Kantharia, G.P. with Ms. Jyoti Chavan, Addl. G.P. with Ms. Jaymala J. Ostwala, Addl.G.P. with Ms. Gaurangi Patil, AGP for Respondent Nos. 1,3,5,6,7,8 and 9 _______________________________________ CORAM : ALOK ARADHE, CJ. AND M.S. KARNIK, J.
DATE : 26th MARCH 2025 P.C. :
1.
Learned Counsel for Respondent No.2 submits that the High Court Administration has approved the plan and has sent the same for approval to the Executive Engineer. The Executive Engineer has prepared the estimate and has forwarded the same to the Superintending Engineer, Public Works Department, for approval.
2.
The learned AGP appearing for the State submits that within two weeks the estimate shall be approved.
1/2
JPP 19. WP 920.2024.doc 3.
The aforesaid submission is placed on record. 4.
List on 2nd May 2025.
( M.S. KARNIK, J. ) ( CHIEF JUSTICE ) 2/2