Bnc Power Projects Limited v. Maharashtra State Electricity Transmission Co. Ltd Through Its Chairman And Managing Director
74-WP-1738-2024.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION WRIT PETITION NO.1738 OF 2024 SATISH RAMCHANDRA SANGAR BNC Power Projects Limited
...Petitioner
SATISH RAMCHANDRA SANGAR Date: 2026.01.14 18:38:19 +0530 V/s.
Maharashtra State Electricity Transmission Co. Ltd. and Anr.
...Respondents
***** Mr.Suraj Desai Almeda, Advocate for Petitioner. Mr.Abhijeet Joshi (Through V.C.) a/w Ms.Srushti More, Advocates for Respondent No.2.
*****
CORAM
:
M.S.KARNIK & S. M. MODAK, JJ.
DATE :
13th JANUARY 2026 P. C. :- 1.
Learned counsel for the Respondent No.2 submits that due to passage of time and as the NOC has been procured, the Petition has become infructuous.
2.
The Petition is disposed of.
(S. M. MODAK, J.) (M. S. KARNIK, J.) Satish Sangar 1/1