IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION WRIT PETITION NO. 2672 OF 2024 Amina Mohammad Ismail Ansari

...Petitioner

Versus

Slum Rehabilitation Authority & Ors

...Respondents

Mr Tanveer Nizam, with Mariam Nizam, for the Petitioner. Mr Jagdish Reddy, for Respondent No. 1-SRA.

Mr Shakeeb Shaikh, with H Diamondwala & Vinay Dali, for Respondent No. 3.

CORAM

M.S. Sonak & Kamal Khata, JJ.

DATED:

9th August 2024 PC:- 1.

Respondent No. 3 is directed to file and serve an affidavit by 14th August 2024 giving full details of the status of the arrears. Learned counsel for the 3rd Respondent states that an amount of Rs. 6 crores has been deposited with the Slum Rehabilitation Authority ("SRA"). That, at least prima facie, is not sufficient, unless, the 3rd Respondent produces on record a chart concerning each of the tenants and the arrears payable to each of the tenants. Digitally signed by SUMEDH NAMDEO SONAWANE Date:

2024.08.12 14:13:31 +0530 SUMEDH NAMDEO SONAWANE 9th August 2024

5-OSWP-2672-2024.DOC 2.

The SRA should also file and serve an affidavit by 14th August 2024 explaining its position on the status of arrears payable to the tenants.

3.

List this matter or 23rd August 2024.