Perfect Infraengineers Ltd And ANR v. The Board Of Directors Of Technology Development Board
34-42-COMS-70-2024.DOC Shephali
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION COMMERCIAL SUIT NO. 70 OF 2024 WITH INTERIM APPLICATION (L) NO. 25074 OF 2024 IN COMMERCIAL SUIT NO. 70 OF 2024 WITH INTERIM APPLICATION (L) NO. 25073 OF 2024 IN COMMERCIAL SUIT NO. 70 OF 2024 WITH INTERIM APPLICATION (L) NO. 25072 OF 2024 IN COMMERCIAL SUIT NO. 70 OF 2024 SHEPHALI SANJAY MORMARE and SHEPHALI SANJAY MORMARE Date: 2024.08.23 18:26:52 +0530 INTERIM APPLICATION (L) NO. 25072 OF 2024 IN COMMERCIAL SUIT NO. 70 OF 2024 Perfect Infra Engineers Ltd & Anr ...Plaintiffs
Versus
The Board of Directors of Technology Development ...Defendant Board
34-42-COMS-70-2024.DOC Mr Mathew Nedumpara, with Honali Korne & Rahul Yadav, i/b Nedumpara & Nedumpara, for the Applicants/Plaintiffs. Mr Harjot Singh Alang, i/b Raval Shah & Co, for Defendant No. 8.
CORAM:
ARIF S. DOCTOR, J DATED:
23rd August 2024 PC:- 1.
Learned Counsel appearing on behalf of Defendant No. 8 has raised a preliminary objection as to the maintainability of the Suit. He submitted that this is a Commercial Suit and there was no mandatory mediation under Section 12A of the Commercial Courts Act. He further submitted that even the prayers that were sought in the the Interim Application were incapable of being granted. He thus sought time to file Affidavit in Reply.
2.
Affidavit in Reply is to be filed and served on or before 6th September 2024. Affidavit in Rejoinder, if any, to be filed and served on or before 13th September 2024.
3.
Lists the matter on 27th September 2024.
(ARIF S. DOCTOR, J)