Derivados Consulting Pvt Ltd v. Platinum Buidcon Pvt Ltd
1 19-CARBP-254-2024.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION Digitally signed by VINA ARVIND KHADPE Date:
2024.10.03 11:20:43 +0530 VINA ARVIND KHADPE COMM. ARBITRATION PETITION NO.254 OF 2024 Derivados Consulting Pvt. Ltd.
... Petitioner V/s.
Platinum Buidcon Pvt. Ltd. And ors.
... Respondents ----- Mr. Rajeev Carvalho a/w Mr. Rohaan Pajnigar i/b. DSK Legal for the Petitioner. Mr.Avinash Joshi a/w Ms. Neeta Patil i/b. Mr. Shreevidya Nargolkar and Mr. S. R. Nargolkar for the Respondent ----- CORAM :
ARIF S. DOCTOR, J.
DATE :
30TH SEPTEMBER 2024 P.C. :
1.
This Petition is filed under Section 9 of the Arbitration and Conciliation Act, 1976.
2.
Learned counsel appearing on behalf of the Respondents today sought time. On the last occasion, I have recorded that the time had been sought by the joint request of the parties. Today, I am informed that the amount which is claimed by the Petitioner is the amount which is not very large and according Vina Khadpe, PS
2 19-CARBP-254-2024.doc to the Petitioner it is an admitted amount.
3.
Hence, in order to enable the parties to make an attempt to amicably th October, 2024. It is made clear that if on the resolve the same, stand over to 14 next date there is no resolution to the disputes between the parties, the Court shall proceed with the hearing of Section 9 Petition and Section 11 Application i.e. CARAPL/27758/2024.
4.
To be listed alongwith CARAPL/27758/2024.
(ARIF S. DOCTOR, J.) Vina Khadpe, PS