The Branch Manager Universal Sompo General Insurance Co. Ltd v. The Permanant Lok Adalat Mumbai And ANR
7-18-wp128-2025&Ors.modified.doc VRJ
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION WRIT PETITION NO.128 OF 2025 WITH WRIT PETITION NO.129 OF 2025 VAIBHAV RAMESH JADHAV VAIBHAV RAMESH JADHAV Date: 2025.02.10 17:16:38 +0530 WITH WRIT PETITION NO.130 OF 2025 WITH WRIT PETITION NO.131 OF 2025 WITH WRIT PETITION NO.132 OF 2025 WITH WRIT PETITION NO.133 OF 2025 WITH WRIT PETITION NO.134 OF 2025 WITH WRIT PETITION NO.135 OF 2025 WITH WRIT PETITION NO.136 OF 2025 WITH WRIT PETITION NO.137 OF 2025 WITH WRIT PETITION NO.139 OF 2025 WITH WRIT PETITION NO.141 OF 2025 The Branch Manager, Universal Sompo General Insurance Co. Ltd.
... Petitioner V/s.
The Permanent Lok Adalat Mumbai, at Bandra & Anr.
... Respondents Ms. Kalpana Trivedi for the petitioner in all writ petitions.
Ms. Dhruti Kapadia, AGP and Ms. Savina R. Crasto, AGP for the State-respondent.
7-18-wp128-2025&Ors.modified.doc
CORAM
: AMIT BORKAR, J.
DATED : FEBRUARY 5, 2025 P.C.:
1.
In all these writ petitions the challenge is to the imposition of interest by the Permanent Lok Adalat under the provisions of the Legal Services Authorities Act, 1987.
2.
Learned advocate for the petitioner states that the principal amount has been deposited with the respondent No.2/original complainant. Therefore, to the extent the Permanent Lok Adalat grants interest @ 9% and 15% per month, said part of the Award of the Permanent Lok Adalat granting interest is stayed till 20 February 2025.
3.
Stand over to 20 February 2025.
(AMIT BORKAR, J.) Note:
This order is modified as per order dated 10 February 2025.