Trishul Construction Co v. City And Industrial Development Corporation Ltd. And ORS
907-aswp864-2024.doc AGK
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION WRIT PETITION NO.864 OF 2024 Trishul Construction Co.
... Petitioner V/s.
City and Industrial Development Corporation Limited & Anr.
... Respondents Mr. Navroz Seervai, Senior Advocate with Mr. Rohaan Cama, Mr. Sanjay Udeshi, Mr. Aditya Udeshi, Mr. Rahul Sanghvi, and Mr. Netaji Gawade i/by M/s. Sanjay Udeshi & Co., for the petitioner. Digitally signed by ATUL GANESH KULKARNI Date:
2024.07.24 15:21:32 +0530 ATUL GANESH KULKARNI Mr. Chetan Kapadia, Senior Advocate i/by Ms. P.M. Bhansali for respondent No.1 - CIDCO.
Mr. P.P. Kakade, Government Pleader with Mr. O.A. Chandurkar, Additional G.P. and Mrs. G.R. Raghuwanshi, Additional G.P. for respondent No. 2 - State.
CORAM
: DEVENDRA KUMAR UPADHYAYA, CJ & AMIT BORKAR, J.
DATED : JULY 24, 2024 P.C.:
1.
Learned senior advocate representing City and Industrial Development Corporation Limited (CIDCO) is granted one week's time to file affidavit-in-reply to the amended portion of the writ petition after serving a copy thereof upon the learned senior counsel representing petitioner, to which a rejoinderaffidavit may be filed, if any, by 5 August 2024.
907-aswp864-2024.doc 2.
Learned senior advocate for CIDCO, on the basis of instructions, states that the last date of receiving bids has been extended till 7 August 2024.
3.
Stand over to 5 August 2024. To be placed high on board.
(AMIT BORKAR, J.) (CHIEF JUSTICE)