← Library
Bombay High CourtWP/1459/2024dismissed

Sai Enterprises Shirol Thr. Its Proprietor And ORS v. State Of Maharashtra Thr. Its Secretary Public Works Department And ORS

2024-06-28Hon'Ble The Chief Justice , Hon'Ble Smt. Justice Bharati Dangre2 pages

23-WP-1459-2024+ Pdp

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 1459 OF 2024 WITH INTERIM APPLICATION NO. 7172 OF 2024 WITH WRIT PETITION NO. 1460 OF 2024 WITH INTERIM APPLICATION NO. 7171 OF 2024 Sai Enterprises Shirol through its Proprietor & Ors.

..Petitioners

Versus

State of Maharashtra & Ors.

.. Respondents CORAM: DEVENDRA KUMAR UPADHYAYA, CJ. & AMIT BORKAR, J.

DATE:

28th JUNE, 2024 P.C.:

Interim Application No. 7172 of 2024 & Interim Application No. 7171 of 2024:

1.

By moving these Interim Applications amendment is the writ petitions has been sought for challenging the work order and also for impleading the person in whose favour work order has been issued.

2.

Since the amendment sought is consequential, the Interim Applications are allowed in terms of prayer clause (A). 3.

Let necessary amendment be incorporated by the learned counsel for the petitioners within a week. Reverification is dispensed with.

23-WP-1459-2024+ Writ Petition Nos. 1459 and 1460 of 2024:

4.

Issue notice to newly impleaded respondent no.5 in both the petitions, returnable on 2nd August, 2024. (AMIT BORKAR, J.) (CHIEF JUSTICE) Digitally signed by PRAVIN DASHARATH PANDIT Date:

2024.06.28 17:42:05 +0530 PRAVIN DASHARATH PANDIT