Crescent Builders v. State Of Maharashtra And ORS
LSP 52 wp 6454.24.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION Writ Petition No. 6454 of 2024 M/s. Crescent Builders ...
Petitioner V/s.
State of Maharashtra and others ...
Respondents.
Mr. Rajesh Ranglani h/f. Minal Chandnani for the Petitioner. Ms. Tanu Bhatia, AGP for Respondent Nos.1 and 2-State. CORAM : M.S. KARNIK & S.M. MODAK, JJ.
DATE : 5th January 2026.
Digitally signed by LATA SUNIL PANJWANI Date:
2026.01.07 11:54:42 +0530 P.C. :
LATA SUNIL PANJWANI The learned AGP has placed on record a copy of the communication dated 8th May 2024 of the Competent Authority and District Deputy Registrar of Co-operative Societies, Mumbai. The Petitioner has prayed for setting aside the order dated 15th April 2024 passed by Respondent No.3 - District Deputy Registrar. 2.
In view of the communication dated 8th May 2024, since no final order was passed as on the date of filing of the petition, the petition is misconceived. In the communication dated 8th May 2024 which is placed on record by the learned AGP, it has been stated that 1 /2
LSP 52 wp 6454.24.doc the matter is pending for orders and that the orders are expected to come in 15 days.
3.
In such view of the matter, the present petition is disposed of with liberty to Petitioner to challenge the order passed by the District Deputy Registrar, Co-operative Societies if the same is adverse to the interest of the Petitioner.
4.
All contentions raised in this petition are kept open. It is expressly made clear that we have not considered any of the submissions raised in this petition on merits. 5.
Writ Petition is disposed of with such liberty (S.M. MODAK, J.) (M.S.KARNIK, J.) 2 /2